Overview
Case summary
This case concerns the distribution of funds held by the Treasury, specifically the 10 percent reserved from payments on a government construction contract. The contractor defaulted, and the surety completed the work. The bank, which had loaned money to the contractor based on an assignment of the reserved funds, claimed a right to those payments. The Supreme Court affirmed the Court of Claims, holding that the assignment was void under Revised Statutes § 3477 and that the surety, having completed the contract, had a superior right to the reserved funds.
Abstract
The case involves a government construction contract where the contractor defaulted, the surety completed the work, and a bank claimed rights to 10 percent reserved funds based on a loan secured by assignment of those funds. The Supreme Court held the assignment void under federal law, affirming the surety's superior right to the reserved funds as the party that completed performance. The judgment of the Court of Claims was affirmed.
Procedural posture
Legal categories
Case record
Issues & holdings
de novo
The court held that the bank acquired no equitable lien and that the assignment was void under federal statute.
Holdings of the court
Timeline
No timeline recorded.
Facts & evidence
Key facts
5 facts- A contractor entered into a contract with the United States for the construction of a custom-house at Galveston.
- The contract provided for a 10 percent reservation from monthly payments.
- The contractor defaulted, and the surety completed the building.
- The bank advanced funds to the contractor based on an agreement that it would receive the 10 percent reserved payments.
- The bank held a power of attorney from the contractor to receive the 'last estimate' from the United States.
Authorities
Legal principles applied
- strict construction of anti-assignment statutes
- surety's right of subrogation